Anticipated Construction Timeline
| Item | Timeframe |
|---|---|
| Design-build Contractor Proposals Due | October 29, 2026 |
| Board of Public Works Contract Approval | January 2027 |
| Design/Architectural Planning for Renovation | January 2027 -January 2028 |
| Construction | June 2028 - August 2029 |
| Grand Opening | September 2029 |
Timeline last updated 10/05/2026 and is subject to change.